Little different than where I came from in the wood plants.
Electricians got blamed for whatever went wrong, even if it was a mechanical part that smashed a sensor of some sort.
Understand from your point Pat. We didnt have E&I techs. We WERE the E&I, along with controls and supply. It was us and 2 programmers.
We unwired motors. Millwrights were SUPPOSED to replace the motor and align, then we connected.
Most of the time, we ended up doing all of it.
That means any down time was against us. Not the millwrights.